A sponsor wants a three-workflow rollout live in 6 weeks. Your team is 3 engineers. Estimates: workflow A (the one the sponsor's staff use daily) is 12 engineer-weeks, workflow B is 20, workflow C is 10. The sponsor asks what can be live on the date. What do you answer?

Select one option
Medium
2Not attempted

You are starting discovery with a new customer. Which are strong first steps? Select all that apply.

Select all that apply

Select all correct options
Easy