Forward Deployed Engineering Practice Question Paper
2 questions. Some questions have more than one correct answer. Submit each one to see the right answer and why. New to the topic? Read the Forward Deployed Engineering guide.
1Not attempted
A sponsor wants a three-workflow rollout live in 6 weeks. Your team is 3 engineers. Estimates: workflow A (the one the sponsor's staff use daily) is 12 engineer-weeks, workflow B is 20, workflow C is 10. The sponsor asks what can be live on the date. What do you answer?
Medium
2Not attempted
You are starting discovery with a new customer. Which are strong first steps? Select all that apply.
Select all that apply
Easy